Bloom Energy said Oracle reaffirmed its commitment to roughly 2.4 gigawatts of fuel-cell capacity tied to the Project Jupiter AI data-center program, Bloomberg and Yahoo Finance reported.
Shares of Bloom Energy rallied after Yahoo Finance reported Oracle had told investors it remained committed to the roughly 2.4 GW arrangement, which underpins Bloom’s role supplying stationary fuel cells for Oracle’s AI campus.

Bloom Energy’s investor page and multiple outlets trace the deal back to an April master agreement in which Bloom and Oracle expanded a strategic partnership for large-scale fuel-cell deployments; Bloom’s press release said the expanded master agreement supported up to 2.8 GW of capacity.
At the same time, Reuters and CNBC reported that Oracle issued a “force majeure” notice tied to Project Jupiter after regulatory delays with natural gas pipeline hookups, a move that analysts said could give Oracle the right to delay payments or timelines if the campus cannot meet its target in 2028.

The juxtaposition — Oracle publicly reaffirming its fuel-cell commitment while also filing a force majeure notice related to Project Jupiter — created market uncertainty about schedule and payment timing, Yahoo Finance and Reuters said.
Bloom’s April press release on the expanded partnership described a master agreement to deploy “up to 2.8 GW” of Bloom fuel cell systems to accelerate AI infrastructure build-out, and later coverage narrowed the near-term installed figure the companies discussed to roughly 2.4 GW tied to Project Jupiter.
Analysts and market reports cited by Yahoo Finance and MarketBeat noted that the force majeure notice does not necessarily mean Oracle will abandon Project Jupiter, but it does “introduce schedule and payment uncertainty” for suppliers and lenders while permitting contractual protections if the project is delayed.
For readers tracking the corporate players behind the cloud-to-AI infrastructure push, Oracle’s broader financial moves and executive prominence in AI remain relevant context: Oracle recently reported Q1 results and raised its FY2027 outlook, and Larry Ellison has been prominent in AI coverage this year, per prior reporting.
Sources
- Yahoo Finance — reported Oracle “reaffirmed” its roughly 2.4 GW fuel-cell commitment and covered market reaction to Bloom Energy shares.
- Reuters — reported Oracle issued a “force majeure” notice tied to Project Jupiter and explained the potential contractual effect on timing and payments.
- Bloom Energy (investor release) — provided the April press release describing the expanded master agreement supporting up to 2.8 GW of fuel-cell capacity.
- CNBC — reported and summarized the force majeure filing and its implications for Project Jupiter’s schedule.